bujagali hydropower project

DOCUMENTS & MAPS

The Bujagali Hydropower Project will comply with strict environmental and other regulatory requirements before construction may begin. Bujagali Energy Limited has completed and submitted several major documents to the Government of Uganda (National Environmental Management Authority) and prospective project lenders (The World Bank Group and others) as part of their comprehensive review of the proposed project.

The documents that we have submitted (to date) appear below and can be accessed by clicking on the title of each. Due to their size, we have segregated maps, charts and other graphics and posted them as separate documents. This will enable you to open and/or print them more quickly.

We invite you to review these documents and submit comments to the National Environmental Management Authority (NEMA) at the address listed below, or provide them directly to us at info@bujagali-energy.com. You may also contact our Bujagali Energy Limited offices in Jinja or Kampala (addresses follow).

National Environmental Management Authority


Executive Director
National Environmental Management Authority
NEMA House, Plot 17/18/19, Jinja Road
P.O. Box 22255,
Kampala, Uganda
(+256) 41 - 25 10 64

Bujagali Energy Limited

Bujagali Energy Limited
Kampala Serena Conference Center
Kintu Road
P.O. Box 36498
Kampala, Uganda
Bujagali Energy Limited
Plot 13 Jackson Crescent
P.O. Box 186
Jinja, Uganda
(+256)(0)43-412-0122


Please go to Interconnection Project to access documents and maps submitted on behalf of Uganda Electricity Transmission Company Limited for its proposed Bujagali Interconnection Project.

Links to Key Documents

PUBLIC NOTICES:

Public notices were issued in the New Vision, Daily Monitor, and Bukedde newspapers on or about September 23, 26 & 27, 2006. The notices are available in English and Luganda:

Social & Environmental Assessment (SEA) Consultation Summary Report release (AUGUST 2006)

DOCUMENTS:

Please be advised that if you have a dial-up connection some large files may take 15 minutes or more to download.
These files are also available via CD-ROM by calling our Bujagali Energy Limited office in Jinja at: (+256)(0)43-412-0122.

To access the "Assessment of Past Resettlement Activities and Action Plan," please refer to Appendix I in the list below.

Hydropower Project: "Social & Environmental Assessment (SEA) Report" (DECEMBER 2006)

Hydropower Project: (DRAFT) "Public Consultation & Disclosure Plan" (PCDP) (SEPTEMBER 2006)

Hydropower Project:"Social & Environmental Assessment (SEA)/Terms of Reference" (SEPTEMBER 2006)

Hydropower Project: "SEA Summary Report" (SEPTEMBER 2006)

NEWSLETTER SUMMARY OF KEY FINDINGS:

September 2006